Your contractor has told you that the equipment you require cannot be delivered until a specific date. You would reflect that in your project plan as:
- A problem or opportunity
- A task
- A constraint
- A milestone
You Answered: A
Correct Answer: C
Constraints are used to identify date limits or restrictions on the start or end of a task. Typical constraints include things like “No earlier than”, “No later than”, and “As Soon As Possible”.