Question

Your contractor has told you that the equipment you require cannot be delivered until a specific date. You would reflect that in your project plan as:

  1. A problem or opportunity
  2. A task
  3. A constraint
  4. A milestone

You Answered: A
Correct Answer: C

Constraints are used to identify date limits or restrictions on the start or end of a task. Typical constraints include things like “No earlier than”, “No later than”, and “As Soon As Possible”.